According to IMNA News Agency from East Azerbaijan, Musa Alipour Zenozi stated to reporters this afternoon _Saturday, July 29th_: In the workshop for producing segmental parts for the Qaramalek non-level intersection, 120 pieces have been produced to be installed on the deck of this overpass bridge, and 55 of these pieces have been installed so far.
He added: “After production, these parts were transported to the project site located in Qaramalek Square for installation on the deck of the Qaramalek overpass bridge and will be used to complete the non-level intersection.”
The mayor of Tabriz’s 2nd District noted: “With the completion and operation of this project, which is being constructed with 68% physical progress on Kargar Boulevard with a special and new architecture, 530 meters long and 24 meters wide, we will witness a major traffic transformation and facilitate the movement of citizens in the western area of Tabriz and smooth urban traffic.”